1. Right Answer: C
Explanation: A trigger is a warning sign or a condition that a risk event is likely to occur within the project.Incorrect Answers:A: Issues are events that come about as a result of risk events. Risks become issues only after they have actually occurred.B: A contingency response is a pre-planned response for a risk event, such as a rollback plan.D: A threshold is a limit that the risk passes to actually become an issue in the project.
2. Right Answer: A,C,D
Explanation: The primary goal of qualitative risk analysis is to determine proportion of effect and theoretical response. The inputs to the Qualitative Risk Analysis process are: Organizational process assets Project Scope Statement Risk Management PlanRisk Register -Incorrect Answers:B: The cost management plan is the input to the perform quantitative risk analysis process.
3. Right Answer: C
Explanation: Complexity of the organizational structure will have the most significant impact on the Information security governance model. Some of the elements that impact organizational structure are multiple business units and functions across the organization.Incorrect Answers:A: Currency with changing legislative requirements should not have major impact once good governance models are placed, hence, governance will help in effective management of the organization's ongoing compliance.B, D: The numbers of employees and the distance between physical locations have less impact onInformation security models as well-defined process, technology and people components together provide the proper governance.
4. Right Answer: B
Explanation: As business case includes business need (like new product, change in process, compliance need, etc.) and the requirements of the enterprise (new technology, cost, etc.), risk professional should utilize this for implementing specific risk mitigation activity. Risk professional must look at the costs of the various controls and compare them against the benefits that the organization will receive from the risk response. Hence he/she needs to have knowledge of business case development to illustrate the costs and benefits of the risk response.Incorrect Answers:A, C, D: These all options are supplemental.
5. Right Answer: B
Explanation: Risks that are now outdated should be closed by the project manager, there is no need to keep record of that.Incorrect Answers:A: Risks do not go into the issue log, but the risk register.C: Identified risks are already in the risk register.D: Risks with low probability and low impact go on the risk watchlist.
Leave a comment