1. The project is made by the supplier in the new project. Which of the following documents must be potential suppliers leave as a project manager can find the best suppliers for the project?
A) SLA B) RFP C) None D) Change Request E) SOU
2. The project manager was asked to prepare and present an overview of the implementation phase. Which of the following is the best audience for this review?
A) project teams B) important stakeholders C) business analyst D) seller E) Middle
3. Project Manager frees resources and archiving of documents. Which of the following stages, the project is likely?
A) closing B) Monitor and control C) None D) Plan E) initiation
4. The new player was added to the project with a bag of $ 850000. The party raised the request to change the five to BPC; Two of them were approved and three waiting for the first examination. Given the project is 0.89 and the CPI and SPI 1,14 approved to be implemented, which of the following should the project last?
A) Assessing the impact and justification. B) None C) Implement the changes. D) Update documents and plans. E) Identify and document risks.
5. The team was formed and assigned to the project to reduce the recent unexpected cost overruns means of production. Which of the following tools should choose a project to determine the possible origin of the higher costs?
A) Pareto chart B) graphics run C) Christmas tree diagram D) technology system E) None