1. Outsourcing Project team member approaches to the manager and complained that the agreement does not allow overtime. The project manager has been fast-tracked in tasks that require more time. Which of the following documents, the project manager does not belong?

A) SOU
B) MOU
C) MOA
D) SLA
E) None


2. The company decides to give a large part of its development to another company for the management and completion, because the company is qualified resources to perform the work. This approach is called:

A) reinforcing the staff
B) work movement
C) resource leveling
D) outsourcing
E) None


3. One of the team members has been assigned a new task during the meeting. a team member does not complete the task by the end of the phase, and PM is looking for evidence to force the issue. Which of the following can help in this situation?

A) None
B) ~~ connection POS = Drop
C) These programs
D) action points
E) error protocol


4. The project manager is assigned to the current project. Which of the following is the first manager of document security should be revised?

A) ~~ connection POS = Drop
B) project structure
C) project plan
D) action points
E) None


5. PM prepares to meet kickoff planning phase. It is extremely important for the team to focus on the expected results of the meeting. Which of the following best describes what the PM should work on first?

A) project structure
B) risk register
C) Responsibility Assignment Matrix
D) , Agenda of the meeting
E) project plan


1. Right Answer: C
Explanation:

2. Right Answer: D
Explanation:

3. Right Answer: E
Explanation:

4. Right Answer: B
Explanation:

5. Right Answer: A
Explanation: